Hazard removal works in the Beauty Point area.

Published Thu 21 Aug 2025

Members please be aware of the below notice to Mariners, works in the area of the Club are the removal of the old mooring dolphin near the PDYC start line and checking on the remains of the old dolphins off the southern end of the AMC wharf.

Works in the PDYC area are scheduled from Monday 25th to Saturday 30th August. Sketch of the planned barge anchor pattern (now below) with wires generally go to seabed within 30-50m from the barge.

Huge thanks to Tasports and all involved in this project, making our playing field much safer! 

M281-25 River Tamar, Beauty Point – Pile Removal and Replacement

Mariners are advised that hazard removal works will be carried out in the Beauty Point area using TasPorts’ anchored barge TB Massif from 25 August 2025 until 19 September 2025.

The works will involve diving operations, piling and various barge and small vessel movements in the area.

Mariners should navigate with caution and keep clear of all works and associated vessels.