EnviroSlip Project Update to Members 9

Published Sun 12 May 2024

EnviroSlip Project Update to Members 9

Lots of concrete and moving to completion at pace is the weekly wrap, the Kemps Parade kerb is complete and the first of the capture pit slabs have been poured on the east slip bays 13-17.

Two more days of concreting will see the bays 13-17 complete, and the crew from RMB Construction move onto completing the new bay 1 and the slip incline, now that the new kerb is in place to work up to.

Huge thank you to the 15 or so members that gave up their time on Saturday, to clean up the eastern side of the slip, fantastic job with the hardstand surface, all clean in preparation for lots of use very soon.

 

Works coming up.

This week along with the concreting in the slipway, back filling along the new kerb line will get underway, allowing preparation for the new seal.

The road will not be closed, but please be aware that access may be restricted at times with excavator and trucks working along the road edge. 

As noted, access to the Trailer Park will continue by the Southern gate ONLY, access will still be by a member key if gate is locked. If you have not been to the Club for a while, have a drive by and check out the progress, when you are at the Club, please remember the slipway is a construction site under the control of the RMB Construction, so there is no access. We note that you may see some Club members on the site occasionally assisting with the electrical install, and other items, please still respect that the site is restricted access and do not enter.