EnviroSlip Project Update to Members 8

Published Thu 02 May 2024

EnviroSlip Project Update to Members 8

A week of small jobs, but big steps forward, is the wrap for the past week. The biggest step forward is the whole of the Club and grounds is now connected to the new 63mm site water main and there is huge improvement in water flows and pressure from all the taps, with all the corroded 1" pipes galvanised now bypassed!

All the Enviroslip treatment tanks and pump pits are in place and ready to connect, as we roll into commissioning the system later in May, so we are starting to get a final picture of how the Enviroslip will look.

Works coming up.

The construction of the new kerb along the East side of Kemps Parade, will take place on Monday 6th May. The road will not be closed, but please be aware that access will be restricted when concrete trucks are feeding the kerb machine, so please use caution if you are going to the Club on Monday and be prepared to not be able to get to the main parking area. 

The kerb has a 7-day cure period, before the gap between the new kerb and the existing pavement can be filled, so please keep off the kerb till access is confirmed.

As noted, access to the Trailer Park will continue by the Southern gate ONLY, access will still be by a member key if gate is locked. If you have not been to the Club for a while, have a drive by and check out the progress, when you are at the Club, please remember the slipway is a construction site under the control of the RMB Construction, so there is no access. We note that you may see some Club members on the site occasionally assisting with the electrical install, and other items, please still respect that the site is restricted access and do not enter.