EnviroSlip Project Update to Members 7

Published Thu 25 Apr 2024

EnviroSlip Project Update to Members 7

Another big week with the slipway historically changed this week with the first of the new concrete poured on the western side Enviroslip bays.

Again, a big thankyou to the construction team lead by RMB construction with Pro-Dig and Clean Green Plumbing, for punching through the Trailer Park capture pit and slab during last week to keep the Sailing program running last Sunday for the second weekend of the 2 Handed Series.  

 

Works completed update:
Concrete poured in the non-pit rail sections of bays 13-17.
Travers bay graded slab poured.
Trailer Park capture Pit and Slab finished.
Last of the inground tanks installed.
Gravel prep completed on Slip Bay 1.

Works to come:
Set up of treatment tanks and oil water separator.
New graded drainage slabs between rails on Bays 13-17.
Pouring of Kerb and channel then a 7-day cure period.
Continuation of electrical cable install. 

As noted access to the Trailer Park will continue by the Southern gate ONLY, access will still be by a member key if gate is locked.If you have not been to the Club for a while, have a drive by and check out the progress, when you are at the Club, please remember the slipway is a construction site under the control of the RMB Construction, so there is no access. We note that you may see some Club members on the site occasionally assisting with the electrical install, and other items, please still respect that the site is restricted access and do not enter.